SCTID Projected Application Timeline
Project Applications submitted to SCTID: By April 1
SCTID Application submitted to ODOT: May 1-May 31
Statewide TID project funds awarded: July
Application Requirements
Engineer's Estimate with prevailing wage and useful life statement
Estimate must contain specifications for project
Estimate must contain Engineer's stamp
Resolution from the City stating the amount of the match to be contributed to the project
A PDF Map showing the location of the project
A brief summary of how the project will benefit either:
Economic Development
Transportation factors
Fund planning project
A resolution stating the acceptance to pay the 3% of the grant award success fee to the Seneca County TID
Submit the Applications to the Following:
PREFERED METHOD OF SUBMISSION IS VIA EMAIL IN PDF FORMAT
MARK ZIMMERMAN, SENECA COUNTY ENGINEER
mzimmerman@senecacountyohio.gov
3300 Infirmary Rd
Tiffin, OH 44883
and
Seneca Regional Planning Commission Attn: TID
jadkins@senecacountyohio.gov
109 S Washington St, Suite 2206
Tiffin, OH 44883